From: Jeanne Brennnan Wiebracht > Sent: Wednesday, November 15, 2017 4:28 PM To: jeffrey E.*; 'ann rodriquez'; 'Danny Vicars' Cc: Subject: WAPA UPDATE WAPA UPDATE=/o:p> I =poke with the line crew working on the Cabrita Road. The process is = line crews lay the poles, pulls the line, energizes from one access point=to another, then notifies WAPA the access points have been energized . WAP= then follows behind to turn power on. =o:p> As of today, a crew is working on=the Cabrita Road laying the poles near the beach at the Ritz ( near (Si ac=ess point ). They explained that they are moving slower than u=ual as land is below sea level and they need additional equipment to recur= the poles in the sand. He estimated 10 to 14 days before the poles =re completed out to the end of the point. And a number of days=later to pull the wire - but in his words this was a very rough esti=ate . He did say as soon as we see the wires being pulled they=are getting close to energizing. &=bsp; Danny and Anna can you respond with a c=nfirmation ASAP that the access point to LSJ ( on the ST. Thomas side) and=all the equipment/transformer etc. required to receive current is functional. Otherwise=WAPA will not hook up. I include Jermaine on the email too =s the fiber cabinet is on the pole and needs to be accessed as well. =C2 I will keep you updated on the line crew pulling of the wire. J=anne From: jeffrey E. [mailto:[email protected] Sent: Wednesday, November 15, 2017 10:29 AM EFTA_R1_01731714 EFTA02566490