From: To: Jeffrey Epstein <[email protected]> Cc: 20/TO Ranch Subject: ZDC Project Update Date: Fri, 05 Jun 2015 13:52:08 +0000 Project Status below for your review Movie Room: New equipment install completed, One blown sub woofer, options to be forwarded Gun Cabinet panels leather inserts completed Chaises and Chairs ordered, estimated delivery last week of July Pool/Gym sound system: Completed Surge Protection: 90% Complete Main Distribution Pumps: New Skid ordered, estimated delivery, week of the 8th June Install will take 3 days Present status, have one pump running, manual operation only,. Outdoor Rugs: Ordered, expect delivery, week of the 8th June Bunkhouse Sofa: Ordered, delivery estimated last week of July Outside Furniture Lodge: Purchasing wood 8th June, completion end of July JJ's: Bunkhouse windows delivered yesterday, work starts today Lodge Deck Roof, completed LV Tennis Court resurface, weather delayed, work started Tues this week Painting: Workshop and wash bay interior completed Pole Barn and Eves of Workshops completed Picket Fences RC and LV Fence completed Bunk House exterior to begin once windows are installed Chess fountain basin sealed, completed RC Bumpers week of the 8 June MH and Estancia doors waxing week of the 8 June Masterbed room window sills week of the 8 June Landscaping: New Sod at Pool Area, complete Hydroseeder, on sight, hydroseeding MH and LV next week Planter beds MH, anticipate to start clearing 17th June Log Cabin Grading, anticipate to start rock collecting etc 15th June Working on new design to include terraces New JD Ride on Mower RC, pickup 8th June Cottonwood trees RC end of June EFTA00642764