{"efta_number": "EFTA01977455", "page_count": 2, "url": "https://epstein-data.com/EFTA01977455", "pdf_url": "https://epstein-data.com/pdf/EFTA01977455.pdf", "pages": [{"efta_number": "EFTA01977455", "page_number": 0, "text_content": "JE Punch List - October 29, 2012\n1. Clean Up - make as many barge runs as necessary\n2. Equipment and Vehicles\n- Sell equipment\n-No machinery off the island unless approved\n-Red Polaris Bike - Power Steering Module - incorrect unit arrived, correct unit resent due on site 10/27\n- Lull-replacement parts ordered 10/19 - per Jack to Tropical by 11/1\n- Kawasaki back and bottom cushions ordered 10/3 - per Jack to Tropical by 10/30\n3. Five Palms\n-Outside furniture - tie down cushions to resolved wind issues - COMPLETE\n- Picture frame - on site, 86 x 70 - Sarah to forward selected picture, will frame locally\n-Mirrored siding-reglued 5 more section 10/24, will continue to reglue as sections fall off - 17 new sections and glue\npurchased-on STT 10/27\n- Piano re-tuning - COMPLETE\n4. Grotto\n- Mattress cover-completion expected 10/30\n5. Berm/Top of Hill\n- Hydroseed all top of hill/berm - COMPLETE - rain continues to wash away seed in areas\n6. Triangle\n- Must design triangle - awaiting JE direction\n- Palms will be relocated once Lull is repaired\n7. Flagpole Pool Cabana\n- Furniture - desk from Paris - Sue arranging shipping to STT\n-Pace clock - unit rusted - ordered 2 new units - 1 for backup - due on site 11/8\n- Auto closer on toilet door - David (carpenter) - COMPLETE\n-Add some lights near steps-COMPLETE-JE to review when on site\n8. Floating Dock\n-Jet ski bumpers - complete - this installation has not resolved the issues of protecting the jet skis\n-Sea-Do Jet Ski - will need to review how this unit will be secured at dock\n- Dock box top - one final attempt to refinish - David (carpenter) - due to be completed 10/27\n-Dock boxes - struts to be replaced - David (carpenter) - will review when JE on site\n- \"Walk the plank\" - review material on this & floating dock - \"rubberized material\" - will review when JE on site\n- Dock carpet - at Tropical, sailing 10/31\n9. Chillax Room\n- Requires furniture piece for electrical/media equipment - Sarah forwarded a selection 9/28 & 10/1-awaiting\ndirection\n10. Chillax Bathroom\n- Blue rugs for bathroom & vanity area - please note attached photo showing existing rug which has softened &\nflattened out since its installation. Would suggest review when on site before purchasing\n11. Mechanical Building Transformer - changed out - COMPLETE\n12. Boats\n- Lady G-sell - will remain at Nanny Cay until sold\n- Big N-repair at AYH dock in progress - boxes to be installed 10/30, painting to be begin 10/29 - cylinders to be\ninstalled on LSJ - will discuss timing when JE on site - hydraulic hoses ordered 10/2 - per Jack to Tropical by 10/30\n13. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas - they remain at 85 degrees\n14. Transient Surge Protection - Tropical shipped to Nassau in error - EDA on STT by 11/6\n15. Landscaping - Peter's List\n- Flowers\n- Master Planter\n- High road waterfall - rocks to be installed\nEFTA_R1_00463980\nEFTA01977455\n", "char_count": 2928}, {"efta_number": "EFTA01977455", "page_number": 1, "text_content": "-Line all roads with stones\n- Pop's Garden - require deer protection - Larry will bring electric fencing on plane\n-Shade cloth-adjustments made, have shade cloth to the ground, reviewing propagation of seeds which were planted\n10/16\n- Peter to clean the sides of the road-work in progress\n- Black Heli Under Pads - install at top of bike path at MC-1,206 sq. ft - Geoblock 5150 purchased-on STT 10/27\n- Review growth of sea grape - engineering area - transplanting has not worked - review purchasing small plants\n-Take down the ropes at the end of the month on the trees - COMPLETE\n16. Roads\n- General re-grading of roads - ongoing - Peter\n- Betteroads quotes from triangle to crest of road above gym - Asphalt - $71,5000, Concrete - $103,600. Brice to review\nwith JE when on site\n17. Library\n- AC quote forwarded to Rich Barnett, who had design concerns, awaiting reply from vendor\n18. New Employee Bathrooms\n19. Gym\n- New punching bag - installation of the speed bag - David (carpenter) - old unit removed awaiting direction from JE\n- New front & back doors installation - David (carpenter) - COMPLETE - painting of doors to be completed 10/27\n20. Beach Office\n- complete electrical overall required\n-waterproofing/sealing/painting/replace rotten wood - David (carpenter) - will begin 10/26\n21. LSJ Mooring - Darren spoke with Army Corp 10/17 - still working on environmental report, will forward ASAP\n22. Hangar\n- Fuel Containment Pad - via Cecile 10/25- there is an issue with the site possibly being in a flood zone. Reviewing\nwith Jaredian Design Group (John Woods).\n23. Steel shed - Buck Steel drawings on site. Shed ordered, will schedule removal of existing bolts patterns and\ninstallation of new\n24. Equipment Purchase and Delivery\n- (3) Terex RL-4000 6kW Light Tower systems - at Tropical, sailing 10/31\n-(1) Skid steer forks -per Jack to Tropical by 10/30\n- (1) 2012 John Deere 5101E tractor with 553 loader and 8' blade - delivered to Tropical 10/25- will sail as soon as\nspace is available\n-(1) 2003 Genie Z60/34 Boom lift- delivery to Tropical by 11/9\n- (2) 2013 S4-Express electric golf cars purchased-on STT 10/27\n-(1) 2012 Ford F450 Dump truck-on site\n-(1) 2012 JCB 8035Z Mini Excavator purchased - $39,455 10/22 - awaiting buckets from UK 11/2 - delivery to Tropical\n11/5\n25. LSJ Mats - for all locations - ordered 9/22 - Logo approved 10/16 - in production\n26. Containers - 2 off site 10/18, 3rd off site 10/20. RO & Generators in remaining container, will be removed once Lull\nrepaired\n27. Stone Walls - Repair work to replace missing loose stones - Gerry & TJ working as time permits\n28. Part Time Employees - focus on finding housekeepers - have a potential candidate, working the next week.\nInterviewing 2 others on 10/27 via contact in Botany Bay. Employment Company Anna found was unable to provide\nanyone.\n29. Heli Pad - wind sock for Heli pad on site. New wind sock assembly ordered by Larry awaiting ETA to LSJ\n30. Cisterns - need to be cleaned /sealed. Vendor on site 10/20 to review scope of work - quoted expected 10/30\n31. Solar - lights installation COMPLETE - JE does not like the \"white light\", likes a \"soft white\" light - JE to review when\non site\n- Revised proposal from Pure Logic submitted to JE via email 10/22\n32. Master Bedroom - door sliders require waxing and alignment - David (carpenter) - COMPLETE\nEFTA_R1_00463981\nEFTA01977456\n", "char_count": 3377}]}