{"efta_number": "EFTA01976576", "page_count": 3, "url": "https://epstein-data.com/EFTA01976576", "pdf_url": "https://epstein-data.com/pdf/EFTA01976576.pdf", "pages": [{"efta_number": "EFTA01976576", "page_number": 0, "text_content": "JE Punch List — November 13 2012 \n1. Clean Up - make as many barge runs as necessary \n2. Equipment and Vehicles \n- Sell equipment \n- No machinery off the island unless approved \n- Lull — replacement parts — on site. Sub Boom Assembly ETA LSJ 11/16 \n3. Five Palms \n- Picture frame — on site, 86 x 70 — Sarah forwarded 3 proofs for JE to review 11/8, will frame locally \n- Wooden Bases — for sculptures — David — in production ETC 11/21 \n- Mirrored siding — continue to reglue as sections fall off, 2 sections off, area needs to dry before installation can be \ncompleted \n- Piano/Stool —to be relocated to hanger after visit \n4. Grotto \n- Mattress cover — completion delayed due to owner travelling to northeast — completion expected 11/14 \n5. Berm/Top of Hill \n— Brice investigating a wood/paper combination material for hydro-seeding. Distributor found, sourcing material \n- Pergola construction for high road benches — David — require design details/number from JE \n6. Triangle \n- Palms - relocated once Lull is repaired \n- Gorilla — to be relocated to top of triangle once Lull is repaired \n- Installation of lights — final light installation will be completed once Gorilla is relocated \n7. Flagpole Pool Cabana \n- Furniture — Desk - ETA STT 12/10 \n- Area Rug — JE requested 11/7 either soft white with black design or plain white extra soft rug - Sarah \n- Pace clock — ordered 2 units due on site 11/8 delay due to Sandy ETA 11/14 \n8.  LS1 Dock \n- Dock box top & seat — Installed. Require more coats for UV Protection, which will be completed after visit \n- Dock Carpet — David will install early Dec \n9. Dock Boxes \n- David will attempt to refurbish & replace all rotten lids & bases on existing boxes \n10. Chillax Room \n— Requires furniture piece for electrical/media equipment - Sarah forwarded another suggestion 11/13 \n11. Chillax Bathroom \n- Walls in vanity area to be painted —1E to select color/style. \n- Install Robe Hook on bathroom door —require location/height. Sarah has ordered correct hook 11/11 \n12. Boats \n- Lady G — sell — will remain at Nanny Cay until sold. LV investigating selling in NJ \n- Big N — rams/boxes installation & painting — complete. Hydraulic hoses installation & final electrical completion \nexpected 11/14 \n- Midnight Express — sell - LV investigating selling in NJ. Advertising locally \n— Purchase New Dingy — sourcing locally \n13. AC - Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees \n14. Transient Surge Protection, Blue Storage Bins & Safety Glasses —\nTropical shipped to Nassau in error, customer who received goods is refusing to return items. Awaiting claim forms \nfrom Tropical. Per JE direction reordered 11/09 \n15. Old Floating Dock —\nBreak down and Dispose - begin 11/12 \n16. Landscaping— Peter's List \n- Line all Roads with Rocks & Rocks for Waterfall —Top Priority \n- Beach 3 — cleaned & graded - work to begin 11/14 \nEFTA_R1_00462783 \nEFTA01976576\n", "char_count": 2963}, {"efta_number": "EFTA01976576", "page_number": 1, "text_content": "- Rubbish Dump - regrade, bern placement along side road \n- Transformer area on back high road — plant out \n- Cutting Flowers/Vegs — Brice has purchased wide variety of seeds - planted 11/11 \n- Master Planter — JE to speak with Peter when he is back on duty \n- Pop's Garden — electric fence — ETA STT 11/14 \n- David to make planter boxes — in production, 1 complete. \n- Black Heli Under Pads — install at top of bike path at MC — Installation to begin 1/10 \n- Sea Grape — contacted PR sourcing prices expected 11/14 \n- 20 x 15ft Coconut Palms — for engineering area — ordered 11/9 ETA L.5112/1 \n17. Roads \n- General re-grading of roads — ongoing — Peter \n- JE requested investigating surfaces that can handle the weight of the heavy equipment \n18. Library \n- AC quote forwarded to Rich Barnett, who had design concerns. Plans forwarded to Atlanta 10/30, engineer will \nanswer concerns & develop control designs, EDA 11/16 \n19. New Employee Bathrooms \n- research \"outhouse \"option \n20. Gym \n- Old Punching Bag to be reinstalled — complete 11/13 \n- Glass front fridge on site 11/15 to be installed — David to trim out location \n- Ballet Room Windows — chipped. Opener needs gluing — will complete after visit \n21. Beach Office \n- complete electrical overall required \n- waterproofing/sealing/replace rotten wood —Complete \n- painting in progress ETC — 11/16 \n22. LSJ Mooring — Darren spoke with Army Corp 10/17 — still working on environmental report, will forward ASAP \n23. Hangar \n- Fuel Containment Pad —\n24. Steel shed — ETA Tropical shipping 12/3, sailing 12/5 ETA STT 12/8 Container will be emptied on LSJ & stored until \ninstallation crew on site, Construction crew ETA 1/11 \n- JE requested extra metal sections & roller door to old engineering area — need to approve layout will forward 11/14 \n- Installation of new bolts — David. Due on site 11/14 \n25. Equipment/Household Purchase and Delivery \n- (3) Terex RL-4000 6kW Light Tower systems — 2 on site, 1 remaining to be picked up 11/16 \n- (1) 2012 John Deere 5101E tractor with 553 loader and 8' blade — ETA LSJ 11/16 \n- (1) 2003 Genie Z60/34 Boom lift — EDA Tropical by 11/8 ETA Sailing 11/26 \n- (1) 2012 JCB 8035Z Mini Excavator purchased - $39,455 — awaiting buckets from UK, one received by vendor, 2nd due \nto vendor 11/16 ETA Tropical 11/19 ETA STT 11/25 \n- Yellow Black Assort Life Jackets — ordered 11/13 \n- Floating Pool Mats — for ocean & pool — ordered 11/7 awaiting shipping details \n- 20ft Floating Trampoline — ordered 11/7 ETA Tropical 12/29 \n- Italian Deck Chairs — awaiting shipping/delivery details \n- Extra Restoration Hardware Cushions ordered 11/10 awaiting delivery date \n- L51 Mats — for all locations Logo approved 10/16 — in production — EDA STT 11/23 \n26. Containers  — 3 off site. RO & Generators in remaining container, will be removed once Lull repaired \n27. Stone Walls \n— Repair work to replace missing loose stones — Gerry & T1 working as time permits \n- Complete Heli Pad Wall — sub contractor forwarded bid 11/12 scope of work & more details required, awaiting \nrevised bid \n28. Part Time Employees — interview scheduled for 11/16 \n29. Heli Pad - wind sock for Heli pad on site. New wind sock assembly ETA STT 11/13 \nEFTA_R1_00462784 \nEFTA01976577\n", "char_count": 3240}, {"efta_number": "EFTA01976576", "page_number": 2, "text_content": "30. Cisterns — need to be cleaned /sealed. Bid approved 11/8 Work to start after 1/10 expected completion by 11/18 \nthen back to complete the Great Room cistern early Feb \n31. Solar —Solar lights to be placed everywhere \n• New Solar Vendor on site 11/8 will forward a proposal within 14 days \n32. Movie Screen — investigating purchase Stewart Screen & new Blue Ray DVD Player — will review with Larry while on \nsite 11/141 \n33: Pebble Beach House — fan ordered 11/8 - ETA NYC 11/23 to be brought down on plane \nEFTA_R1_00462785 \nEFTA01976578\n", "char_count": 542}]}