{"efta_number": "EFTA01147446", "page_count": 2, "url": "https://epstein-data.com/EFTA01147446", "pdf_url": "https://epstein-data.com/pdf/EFTA01147446.pdf", "pages": [{"efta_number": "EFTA01147446", "page_number": 0, "text_content": "Punch List - June 6, 2012\n1. Five Palms - TOP PRIORITY\n- Laying conduit and pulling cable - continues\n- Exterior Door Shutters - PO rejected by JE, on hold awaiting design\n- Painting - inside completed 5/30\nOutside to be completed after visit\n- Furniture - Sofa - leather samples JE will review while on site\n- Desk, Rug, Lamps installed\n- Lights - Parrots finished, awaiting approval on down lights\n- Mirrored siding - Panels ordered - EDA to Tropical FL 6/7 - scheduled to sail 6/8, EDA on STT 6/12\nGlue on site\n- Tapestry Molding for Ceiling - bid rejected, need to review design with JE\n- Transformer building - Building 5/31, 5/25 - final electrical hookup 6/8 - temporarily powered by generator\n- Flooring - installed\n- Fire pit - gas and grate coming down on plane\n- Books - books on site will relocate over the week of 6/4\n- Benches - two benches out back\n- Road grading\n2. Grotto -\n- Floor resin\n- Genset wiring - scheduling to be determined\n3. Berm/Top of Hill\n- dirt and rock needs on top of hill needs to go ASAP\n- hydroseed top of hill\n- 4 large planter boxes with small planter inside require construction - size to be determined by JE\n- cleanup and excavate - continues\n- remove rock screener - completed\n4. Engineering/Maintenance Yard\n- Steel Shed - foundation in progress\n- Metal Sheets on old building will be replaced week of 6/4\n5. Triangle-landscaping direction required from JE\n6. Flagpole Pool Cabana -\n- Recovering of sofa/chairs - completed, need to review piping with JE while on site\n- Furniture - review another piece of furniture - Sarah\n7. Entry Tree Lights - installation complete\n8. Solutions for Generators - Sound proofing solution forwarded to JE, require direction, wall built\n9. Tiki - shields with the vendor in Wewak (5/4) - working on the permit to export - will take 1 to 2 weeks\n10. Dock -\n- Decking-replace all damaged boards and carpet complete\n- Floating Dock -\n- Jet ski Docking - review\n- Table/Dock Box - Bill starting 6/4\n11. Kite House - review of wooden outside furniture - Sarah\n12. Chillax Room - requires furniture piece for electrical/media equipment - Sarah\n13. Chilax Bathroom - requires blue rugs for bathroom & vanity area - Sarah\n14. Mechanical Building\n- Replacement Transformer-approved to purchase-ordered\n15. Boats\n- Midnight Express-purchase Yamaha 300 motors, install by Offshore Marine\n- PRD - sell\nEFTA01147446\n", "char_count": 2380}, {"efta_number": "EFTA01147446", "page_number": 1, "text_content": "- Lady G - sell\n- Big N - sell\n- Calypso - refurbish\n16. Gym Road - road grading after Five Palms - continues\n17. Outside Master Bedroom - lock installation 6/2\n18. Timers - review installing timers on air conditioners, irrigation water systems, and lights\n19. Life vests - new life vests, yellow and black, in men's and women's sizes - at least 2 of each, if not 4 in\nunisex size so they can be exchanged - Sarah\n20. Beach lighting - per JE, replace existing transformers for the beach lighting of palms around the salt pond\nand beach\n21. Pergolas - construct 3 pergolas for benches at the top of the hill-continues\n22. Main entrance/gravel/grade - complete\n23. Red Hook Dock - grey carpet and seal Nanna\n24. Wind Door - wind door on kitchen side needs adjusting\n25. Landscaping - gardenias\n26. Solar lights\n27. Roads - grade all roads - Wednesday 6/6 - Tom - please review all roads so you can pitch, drain, with Jules\nand Craig\n28. Library - lights on bookshelves need attention\n-temperature?\n29. Main hill - asphalt path\n30. Master Suite -\n- Exterior doors - John needs to light proof the north doors as well - he only did the east doors\n- Door in dressing area - the heavy mirrored door between the bed and bath is beginning to drag\non the floor\nEFTA01147447\n", "char_count": 1264}]}