{"efta_number": "EFTA00901577", "page_count": 1, "url": "https://epstein-data.com/EFTA00901577", "pdf_url": "https://epstein-data.com/pdf/EFTA00901577.pdf", "pages": [{"efta_number": "EFTA00901577", "page_number": 0, "text_content": "From: \"Gary Kerney\"\nTo: \"Jeffrey Epstein\" <jeevacation@gmail.com>\nSubject: RE:\nDate: Sat, 01 Jan 2011 16:02:58 +0000\nThe deasal equip goes in the 15th will take 10 days to install and then 30 to 45 days to connect all the plumbing and fire up all\nthe equipment\nwe will start the backfilling to get equip access to the west end of the roof monday for parking on the roof as well as access\nshould you go forward with a metal building.we will not fill the back and east end\nFrom: Jeffrey Epstein [mailto:jeevacation@gmail.com]\nSent: Fri 12/31/2010 12:17 PM\nTo: Gary Kerney\nSubject:\nwhen will the desal, electric plant be complete.\nThe information contained in this communication is\nconfidential, may be attorney-client privileged, may\nconstitute inside information, and is intended only for\nthe use of the addressee. It is the property of\nJeffrey Epstein\nUnauthorized use, disclosure or copying of this\ncommunication or any part thereof is strictly prohibited\nand may be unlawful. If you have received this\ncommunication in error, please notify us immediately by\nreturn e-mail or by e-mail to jeevacation@gmail.com, and\ndestroy this communication and all copies thereof,\nincluding all attachments. copyright -all rights reserved\nEFTA00901577\n", "char_count": 1239}]}