{"efta_number": "EFTA00543256", "page_count": 1, "url": "https://epstein-data.com/EFTA00543256", "pdf_url": "https://epstein-data.com/pdf/EFTA00543256.pdf", "pages": [{"efta_number": "EFTA00543256", "page_number": 0, "text_content": "Time Line\n8H\nMay 23-25th: Floors are being refinished\nMay 28th: Painting starts\nJune 11: Ready for furniture\n11P:\nMay 24th: Carpet pulled up/prep work for floor refinish\nMay 31st: Painting starts\nJune 11: Ready for furniture\n10B:\nMay 31st: Office move date\nWeek of June 4th: remove rest of furniture/desks, etc..\nWeek of June 11th: Floors refinished\nWeek of June 18th: Painting starts\nJuly 2: Install furniture\n10F\nMay 31st: Office move date\nWeek of June 4th: remove rest of furniture/desks, etc..\nWeek of June 11th: Floors refinished\nWeek of June 18th: Painting starts\nJuly 2: Install furniture\nEFTA00543256\n", "char_count": 609}]}