{"efta_number": "EFTA00522045", "page_count": 3, "url": "https://epstein-data.com/EFTA00522045", "pdf_url": "https://epstein-data.com/pdf/EFTA00522045.pdf", "pages": [{"efta_number": "EFTA00522045", "page_number": 0, "text_content": "JE Punch List - July 23, 2012 Directives\n1. Clean Up - make as many barge runs as necessary\n- Top of Desal plant\n- Engineering\n- Cleaning the shops - JE would like completed by 7/27\n2. Equipment and Vehicles\n- Sell equipment\n-Bikes should be ready to be sold - no sales without JE approval - bike sale list will be forwarded for JE\napproval 7/25\n-No machinery off the island unless approved\n- Buy new Kawasaki bikes and mules - Rich K negotiating with Vendor\n- Kawasaki parts order submitted twice - awaiting direction\n-Remove all concrete trucks and cement hopper no later than 7/27\n-Cement hopper scheduled to be transported to the Heavy Materials - St. John yard for storage 7/26\npending cost quotes to be forwarded 7/24 for approval\n- Concrete trucks - Monique/Daphne following up on storage and pricing for JE review and approval\n3. Computers\n- Buy new computers - 2 Macs Desktops & 1 Laptop - Captains' Office - ordered\n4. Five Palms\nInternet/Phone Switch installed - fiber to be re-tested 7/24\n-Phone set up left of desk - switch installed 7/20 - COMPLETE\n- Wireless inside only - as of date 7/10 via JE - installation 7/24 - 7/25\n- Computer - as of date 7/10 not required via JE\n- Exterior Door Shutters - estimate forwarded to JE 7/12 - $2,865.00 - awaiting direction\n- Painting - outside to be completed via JE direction\n- Inside to be completed via JE direction-lon- scaffolding is being erected for him\n- Tapestry Molding for Ceiling - lon\n- Furniture - outside furniture ordered - EDA to Tropical 7/24\n- Piano Bench - mounted 7/18 - COMPLETE\n-Piano-schedule to re-tune week of 8/15\n- Picture Frame - measurements forwarded to Sarah - 86 x 70\n- Mirrored siding-liquid nails - will cover entire panel with glue when the next one falls off\n-Transformer Protection Wall - should be built - work began 7/20\n- Floor Gold Lamps - electrical wiring needs to be replaced, completion expected 7/20\n-Fire pit - fix - a new propane tank was installed but it is now empty - Danny and Brian suspect there is a leak -\nthey will investigate 7/24\n5. Grotto\n- Furniture - put back in grotto\n- Curtains - more curtains ordered-cream for the bed at the base of the grotto - expected to arrive to Zorro\nto take to LSJ 7/31\n- Genset wiring - COMPLETE - Danny reviewing auto start from Kite House\n6. Berm/Top of Hill\n-Stone threshold needs total re-do - must be level and straight\n- Boulders - Jules to finish boulder work\n- Electrical - Low voltage transformer in place - placement & connection of lights completed\n- Main transformer on site - installation to begin 7/16\n- Concrete Band - require confirmed mark out via JE\n7. Engineering/Maintenance Yard\n- Steel Shed concrete pad - COMPLETE\n- Metal Sheets - on old building replaced - work to begin 7/18\nEFTA00522045\n", "char_count": 2759}, {"efta_number": "EFTA00522045", "page_number": 1, "text_content": "-Painting - power sanding/rust removal continues - JE would like painting completed by 7/27\n- Engineering Storage & Shelving - work started 7/13 - JE would like completed by 7/27\n- Landscaping-quote for Sea grapes forwarded to JE 7/12 - awaiting direction\n- Landscaper(s) to travel to Josephine's nursery (Coral Bay) - trip is cancelled\n- Engineering water boundary - Jules to finish\n8. Triangle -\n- Landscaping direction required from JE\n9. Flagpole Pool Cabana-\n- Furniture - investigate new desk, new furniture more like Pool Cabana PBI\n- Relocation of orange sofa to Media Room\n- Check water pressure in shower\n10. Floating Dock\n-Jet ski Bumpers -ordered - EDA 7/24\n- Table/Dock Box\n- Dock box handles need completion\n- Dock box top to be resurfaced\n-Dock floors - staining needs completion\n- Swim Ladder - direction from JE on placement required\n- Dive Platform - require construction details\n- Wooden Bumpers - to cover concrete stripping - COMPLETE\n- Painting - Railing, Cross Brackets & Robe Hooks - COMPLETE\n11. Entry Tree Lights\n- Lights on site, electrical installation complete\n12. Solutions for Generators\n-Soundproofing Installation - back wall and door to be completed 7/24\n13. Tiki\n-Shields have been shipped awaiting arrival at Tropical\n14. Kite House\n- relocation of outside furniture from 5 Palms once new 5 Palms furniture on site\n15. Chillax Room\n- requires furniture piece for electrical/media equipment - Sarah\n16. Chillax Bathroom\n- require blue rugs for bathroom & vanity area - Sarah\n17. Mechanical Building\n- Replacement Transformer - estimated date to be shipped from factory (Illinois) 8/21\n18. Boats\n- Lady G-sell-in hurricane storage 7/18\n- Lady K - sell - survey forwarded to Darren & Rich, suggested price $225,000\n- Big N-repair-will go to Subbase Drydock after 8/7\n19. Timers\n- Review installing timers on air conditioners, irrigation water systems, and lights\n- Set all air conditioning to 85 degrees (no need to keep anything cooler)\n- No irrigation week of 7/23\n20. Beach lighting\n- per JE, replace existing transformers for the beach lighting of palms around the salt pond and beach\n21. Transient Surge Protection - will review and forward estimate ASAP - Danny\n22. Ice Maker-ordered 6/21 - vendor will confirm delivery date 7/24\n23. Landscaping\n- Soil material on site - soil removed from beds 7/16-area replanted - COMPLETE\n- Peter to finish transplanting engineering palms - JE to advise where they are to be transplanted to\n- Finish sundial corner (trees, stones, hydro-seed)\nEFTA00522046\n", "char_count": 2532}, {"efta_number": "EFTA00522045", "page_number": 2, "text_content": "Clean up areas marked in paint\n- Prepare banana area for pineapples - awaiting corrected quote for 100 pineapples - Brice to forward\n24. Solar lights - ordered-place every 30 feet - EDA at Tropical 7/24, EDA STT 7/28\n25. Roads-grade - Jules work continues\n26. Library\n- Lights on bookshelves need attention - will complete ASAP\n- Temperature - STABLE\n- Repair hanging wooden louver\n27. Main hill\n- Asphalt path - pour asphalt ends in concrete - top and bottom have been formed, concrete poured at top\nand bottom - stones being placed at bottom - completion 7/25\n28. New Employee Bathrooms\n29. Gym\n- New punching bag - arrived at 71st - will come down on the next plane trip\n- Wiring - balance cables on site - final tidy up 7/20 - COMPLETE\n- Audio cables purchased - installed 7/20 - COMPLETE\n-Yoga room air does not work - Danny to investigate\n30. Benches\n31. Danny Vicars - schedule boat driving lessons\n32. Beach Office\n- complete electrical overall required\n-waterproofing/sealing/painting/replace rotten wood required\n33. LSJ Mooring - Darren will forward to Army Corp for final approval - 7/12\n34. AYH Dock - re-sanding/staining of Nanna dock - COMPLETE\n35. Main Compound Cistern - Demo work complete - confirmed multi leaks - repair work required\n36 Hangar\n- Jermaine to redo internet at hangar - he will forward quote for the rack enclosure 7/24\n- Fuel Containment Pad - draft approved with drainage incorporated, waiting for updated plan\n37. Woodshop Tunnel - floor needs to epoxy\n38. Master bedroom area - add many lights in master bedroom planter\nEFTA00522047\n", "char_count": 1571}]}