FLORIDAN AQUIFER PLANT COSTS Cost Estimate for 10 mgd Floridan Plant Raw Water Wells & Piping $ 13,500,000 Membrane Building w/LPRO system $ 19,000,000 Yard Piping $ 1,500,000 Transfer Pump Station $ 1,000,000 Ground Storage Tanks $ 3,900,000 Dedicated Water Transmission Piping $ 6,000,000 Conceptual Cost $ 64,200,000 General Requirements (2%) $ 1,284,000 Construction Mark-up (3%) $ 1,926,000 Mobilization (2%) $ 1,284,000 Contingency (10%) $ 6,420,000 Engineering and Other Non-Construction Costs (8% $ 5,136,000 TOTAL CONCEPTUAL COST §$ 80,250,000 Assumes no additional cost for land. HOUSE_OVERSIGHT_016661