FIVE PALMS PRELIMINARY SCHEDULE II) a V Task Name Duration Start Finish Predecessors I Ju [,ItAY 5122 1 929 6/5 6/12 6/19 6126 I 7/3 I 7/10 I 7/17 1 - Procurement 98 days Wed 841/11 Fri 10114/11 • 2 Design 23 days Wed 6/1/11 Fri 7/1/11 4144 3 Budgeting 10 days Mon 7/4111 Fri 7/15/11 2 - 0% 4 Approval 5 days Mon 7/18/11 Fri 7/22/11 3 • 5 Site lighting 60 days Mon 7/25/11 Fri 10/14/11 4 6 Coral tiles 40 days Mon 7/25/11 Fri 9/16/11 4 7 Roof trusses 30 days Mon 7/25/11 Fri 9/2/11 4 8 Roof tiles 30 days Mon 7/25/11 Fri 9/2/11 4 9 Exterior doors 25 days Mon 7/25/11 Fri 8/26/11 4 10 Finish hardware 20 days Mon 7/25/11 Fri 8/19/11 4 11 Hurricane shutters 25 days Mon 7/25/11 Fri 8/26/11 4 12 Sun shades 25 days Mon 7/25/11 Fri 8/26/11 4 13 A/C Systems 40 days Mon 7/25/11 Fri 9/16/11 4 14 Generator 60 days Mon 7/25/11 Fri 10/14/11 4 15 Electrical fixtures 60 days Mon 7/25/11 Fri 10/14/11 4 18 17 Sitework 83 days Mon 7/25/11 Wed 11118/11 18 Rough Site 3 days Mon 7/25/11 Wed 7/27/11 4 19 Underground utilities 2 days Thu 7/28/11 Fri 7/29/11 18 20 Install generator 3 days Mon 10/17/11 Wed 10/19/11 14 21 Site lighting 5 days Thu 11/10/11 Wed 11/16/11 24 22 Site concrete 10 days Mon 8/29/11 Fri 9/9/11 29 23 Stonework 20 days Mon 9/12/11 Fri 10/7/11 22 24 Finish grade 3 days Mon 1117/11 Wed 11/9/11 37 25 Landscaping 5 days Thu 11/10/11 Wed 11/16/11 24 26 27 Building 86 days Mon 811/11 Mon 11/28/11 28 Slab 5 days _ . Mon 8/1/11 Fri 8/5/11 19 29 CMU 15 days Mon 8/8/11 Fri 8/26/1128 30 Roof truss system 5 days Mon 8/29/11 Fri 9/2/11 29 31 Roof dose in 20 days Wed 8/31/11 Tue 9/27/11 30FS-3 days 32 Gutter / Downspouts 3 days Mon 9/26/11 Wed 9/28/11 31FS-2 days 33 Set exterior doors 3 days Wed 9/28/11 Fri snotil 31 Critical Baseline Project Summary Critical Split Baseline Split External Tasks Project: Five Pa