From: LAllenby Sent: Saturday, August 8, 2015 2:17 PM To: NYC - Jeffrey Epstein Cc: NYC - Richard Kahn Subject: Re: Paving project additional approval needed Mr. Epstein Per our phone conversation No on swales /wait and see Crusher run ok Please confirm Leighton Allenby Director of Properties > On Aug 8, 2015, at 9:18 AM, LAllenby wrote: > Better Roads was never provided the plans submitted by woods/engineer > Missing on bid: > 32 Swales $42,486 > 3" crusher run base/1360 tons with trucking $90,712. > Asphalt was $512,500 > New Total $645,698 > Time line addition > 5 additional days for swales > 12/15 days for crusher run > Both swales/crusher 17/20 days on top of original timeline > If swales are put in after crusher run snd asphalt add $250 per swale x 32== $8,000. > Also LSJ staff has to put in silt fencing as per plan and permit > I received the correct plans with all this additional information a few da=s ago. Better Roads said they were not given this info by woods. Woods did n=t return Our call. > I strongly suggest doing these roads correctly. We will have a lot of wash=ut, undermining and cracking pavement if we do not do the swales in the cru=her run. > How do you want to proceed > Call me if you need more clarification EFTA_R1_01617309 EFTA02493912