From: Sent: To: Cc: Subject: Saturday, August 8, 2015 1:18 PM NYC - Jeffrey Epstein NYC - Richard Kahn; Allenby, Leighton Paving project additional approval needed Better Roads was never provided the plans submitted by woods/engineer Missing on bid: 32 Swales $42,486 3" crusher run base/1360 tons with trucking $90,712. Asphalt was $512,500 New Total $645,698 Time line addition 5 additional days for swales 12/15 days for crusher run Both swales/crusher 17/20 days on top of original timeline If swales are put in after crusher run snd asphalt add $250 per swale x 32 ==$8,000. Also LSJ staff has to put in silt fencing as per plan and permit I received the correct plans with all this additional information a few days=ago. Better Roads said they were not given this info by woods. Woods did no= return Our call. I strongly suggest doing these roads correctly. We will have a lot of washou=, undermining and cracking pavement if we do not do the swales in the crush=r run. How do you want to proceed Call me if you need more clarification Leighton Allenby Director of Properties <?xml version=.0" encoding=TF-8"b <!DOCTYPE plist PUBLIC "-//Apple//DTD PLIST 1.0//EN" "http://www.apple.com/DTDs/PropertyList-1.0.dtd"> <plist version=.0"> <dict> <key>conversation-idgkey> <integer>107942</integer> <key>date-last-viewed</key> <integer>0</integer> <key>date-received</key> <integer>1439039886</integer> <key>flags</key> <integer>8590195717</integer> EFTA_R1_01617110 EFTA02493749