To: Jeffrey EpsteinUeevacationagmail.comj From: Gary Kemey Sent Fri 7/22/2011 10:56:26 PM Subject Re: Re: One on loader two days at 8.5 hrs and one on truck two days at 8.5 hrs. 34 total man hrs. Sent from my iPhone On Jul 22, 2011, at 6:35 PM, "Jeffrey Epstein" <[email protected]> wrote: operators 34 hours to grade the site, ? how is that possoble. On Fri, Jul 22, 2011 at 5:26 PM, Gary Kerney < = > wrote: building units rate cost excavation 17 $ 25 S 425 base material 10 25 250 labor 25 12 300 compaction 8 15 120 site grade labor operators 34 25 850 labor 34 12 408 generator/bunker excavation 17 20 425 base material 4 25 100 labor 17 12 204 waterproof material 150 3 450 labor 4 12 48 drainage material 1 150 labor 4 12 48 backfill material 4 25 100 labor 17 12 204 sub total S 4082 I can see most of this in my head up thru rough finish at this #. I believe there will be additional costs in this catagory ie: similar to kite house site improvments roads(gravel) stone borders bolders EFTA_R1_00261632 EFTA01861251