To: Gary Kerne From: Jeffrey Epstein Sent: Fri 7/22/2011 10:35:27 PM Subject: Re: operators 34 hours to grade the site, ? how is that possoblc. On Fri, Jul 22, 2011 at 5:26 PM, Gary Kerney •= ,. wrote: building units rate cost excavation 17 $ 25 $ 425 base material 10 25 250 labor 25 12 300 compaction 8 15 120 site grade labor operators 34 25 850 labor 34 12 408 generator/bunker excavation 17 20 425 base material 4 25 100 labor 17 12 204 waterproof material 150 3 450 labor 4 12 48 drainage material 1 150 labor 4 12 48 backfill material 4 25 100 labor 17 12 204 sub total $ 4082 I can see most of this in my head up thru rough finish at this #. I believe there will be additional costs in this catagory ie: similar to kite house site improvments roads(gravel) stone borders bolders wether the $6.000 left in my budget is right is subject to further determination of scope. EFTA_R1_00261519 EFTA01861179