From: emad hanna Sent: Tuesday, May 10, 2011 9:35 To: Jeffrey Epstein Subject: Open Payout Requests Jeffrey, Please advise if you approve any of the =ollowing for payment: Main House =ool Pool contract of $137,800 paid $97,800 balance left is =40,000 this request of payment dated 4-29.11 is for =20,000 Glidden contract of $23,359 paid zero =his request is dated 4-14-11 in the amount of =10,150 Mechanical Building Glidden =ontract of $1,314,166.20 we have paid $1,189,052.20 balance left is =125,114, this request dated 3-25-11 is for $100,165 Thank =ou Emad Hanna Project Controller HBRK Associates 1 EFTA_R1_00120789 EFTA01791121