From: Richard Kahn To: "Jeffrey E." <[email protected]> Subject: PBI Staff house repairs Date: Mon, 08 Jun 2015 13:45:19 +0000 Attachments: Epstein_staff house.pdf i was only able to negotiate a 1.9% discount after you approved job for 29,464.60 to 28,900.00 for work in staff house contractor says work will take about 6 days but cannot begin for 4 weeks please advise if ok thank you Richard Kahn HBRK Associates Inc. 575 Lexington Avenue 4th Floor New York NY 10022 Begin forwarded message: Date: June 6. 2015 at 4:21:01 PM EDT From: To: Subject: Re: Staff house repairs Richard, See revised proposal for the staff house remodel. We can start in 4 weeks and the project will take about 6 days to complete. Please sign and date with a deposit check and forward to: Labonte Construction Services 4165 Linden Ave Palm Beach Gardens Florida 33410 Thank you Dan labonte --Original Message-- From: Richard Kahn To: Dan Sent Fri, Jun 5, 2015 6:31 pm Subject: Re: Staff house repairs EFTA01194776