Punch List — per JE directives as of December 20, 201Chillax room — motion detector switch — should only have one light switch — Gary Moses 2. 5. Flagpole pool - Take the pool cleaners out - Scuppers are either rusted or broken — please send photo to Bart 6. Chillax room - red and blue rug to be tried — the pillows may be the source of the smell 7. Banquette — two tree lights near banquette 8. Gym - Gutter is leaking in the front Punch List — per JE directives December 2, 2011 13. Flagpole bath and cabana — refrigerator 24" wide, 23" deep, stainless steel, and door swing on right - Brice ordered - robe hook outside shower -pool pump insulation for domestic fresh water distribution pump on order — walkway gates schedule — Bill 6. Electrify info center 7. Five Palms — JE approved height — Tom — two high windows 8. Grotto 9. Heli wall 13. Big wind doors lighting - 2 recessed ceiling lights centered on each side of the doors — set on sconce timer 15. St. John terrace — change lights 16. Hangar —floor sanding in progress — 40'X50' area for slab, 3 foot wall around it — containment for ISO fuel tank — bathroom and room divider 17. Plants bought from Italian woman 18. Steel shed for the new workshop area 19. Triangle 20entry tree lights 21. Solar fridge, light, fan for pebble beach 22. Humidifiers — Atlanta Refrigeration speaking to Trane — date? 24. Yellow flowering Alamandra up Old Mill wall and Flagpole hill 25. Beach 3 — containers into back of hill — Peter to grade out 27. Solutions for generators — no provisions for sound dampening — design fault — Maguire contract will be emailed to Gary, Tom, Darren, Brice for research into the matter — Brice adjusted shutter 28. Fire system — not working, Brice creating fire charts for the island 29. Top of hill — CLEAN UP - place garbage in circle — build up 10 feet — new helipad 30. Pool — tiled — Bart — JE selected — LSJ orders — Brice to find out Bart's schedule 31. Library windows — K&S resea