LSJ Cistern Repair Estimate Description of Operation OW Unit Cost! Unit Material Cost Crew Labor Hours Average Crew Rate Labor Cost Subcontractor!E quipment Rental Total Cistern # 1 1 ea S1,080 62 $35 $2,170 $150 $3,400 Cistern # 2 1 ea S900 62 $35 $2.170 $150 $3,220 Cistern # 3 1 ea $480 42 $35 $1,470 $150 $2,100 Cistern # 1 outside wall coating & repair 1 ea $350 24 S35 5840 _S1.190 Allowance for crack repair after cisterns are drained & inspected: # 1 Is leaking and will be repaired with hydraulic cement before coating 1 L g $350 24 $35 $840 $840 Material delivery to Red Hook 1 ton $250 $250 $250 SUBTOTAL $11,000 20% OVERHEAD AND PROFIT 2.200 TOTAL 13,200 (1) Assumes all cisterns are fully d ained by onsite crew (2) Assumes onsite trash disposal (3) Assumes all transportation supplied by LSJ (4) This quote is good for 30 days (5) Upon Notice to Proceed, 100% material & 50% labor deposit required. (6) Balance due upon completion. EFTA01109768