From: Larry Visoski -Ma> To: Je vacation <jeevacation®gmail.com>, Rich Kahn Subject: Nautica Date: Tue, 24 Jan 2017 15:43:46 +0000 Inline-Images: IMG_0162.JPG; IMG_0144.JPG; IMG_0139.JPG; IMG_0137.JPG; IMG_0135.JPG; IMG_0140.JPG; IMG_0142.JPG; IMG_0155.JPG Jeffrey Sea trial Feb 6th is a real date, fine tuning and final completion has taken longer than expected., tube install is taken 2 weeks, finishing up end of this week. Viewed the boat yesterday, photos below, New custom Bow rails installed, Eletric rear bench installed, . Silivio the Tube person all mechanical work to be completed Next Friday, Feb 3rd. Sea trial Feb 6th„ I also met with an electrician, to wire Generator, Shore Power and AC unit, he brought up wire issues that could case Eletric Shock to a person swimming near the boat, I've not familiar with this„ I'll fwd his quote to you and Carlos, for approval, I believe it's nessesasy to make all Electrical correct and safe to prevent shock or Fire. labor and parts $4370., EFTA01056189