From: "Jeffrey E." <[email protected]> To: Subject: Re: Date: Tue, 07 Mar 2017 15:43:19 +0000 what happend after no bid recweived on feb 24th? did anyone call them. water softber for master ?? re r. o not sure where we are , and On Tue, Mar 7, 2017 at 11:41 AM, Brice Gordon <S wrote: Jeffrey Switch Service had a 10 week lead time from signing of contract, approval was finally given Feb 1 RO HP Pump replacement 8 to 10 lead time, renegotiated 4-6 weeks, with a savings of 20K plus and a better pump Service is planned for next week. The main reason you have crappy water is Smiley ran out of Calcium Carbonate, Did he ever come up to you and say "Sir I need Calcium Carbonate, I have asked Danny and Anna to order and nothings happened" I assume not. Regarding the Metal Sheds Received Drawings from John Woods Jan 7th Forwarded Drawings to Buck Steel for Bid Jan 17th Revised bids from Buck Steel Received Feb 1 Forward to EB for Bid Feb I, last communication Feb 16 they advising bids would be received Feb 23, nothing as of date. Forwarded to Drawings for Metal Sheds & Huts to Agencios Construction Feb 6th If you wish I can forward all E Mails relating to these topics. I have forwarded proposals from Buck Steel and Agencios to RK for his review regards Brice On Tue, Mar 7, 2017 at 7:38 AM, jeffrey E. <[email protected]> wrote: i am aware . thnks howver it is march , 4 months later . and still nothing resolved. On Mon, Mar 6, 2017 at 10:22 PM, ZM < wrote: Sorry I worked extremely hard on all of these items. Especially RO and Switch Gear Noting Switch Gear issue started in 2013 and RO in 2015 I addressed these issues Nov 2016 after finding out that basically nothing was working, no PMA being completed and everyone was blaming someone else for the issues or ignoring it totally rather than trying to resolve them I'm looking for long term resolve and relationships so this does not happen to you again Working extremely hard to save you e