From: Stephanie Remington To: J <[email protected]> Cc: Richard Kahn s , Da hne Wallace < , michael glidden , Patrick Cena Subject: Progress Report 01'04/19 - 02/17/19) Date: Sat, 16 Feb 2019 14:03:59 +0000 Please note: This is a summary of the last two weeks' focus, not a comprehension of all projects. Carpentry. Repaired coral stone at chillax bath. Cut in sink, cooktop in temporary countertop at FPP Kitchen. Moved kitchen equipment for tiki floor prep. Assist w Tiki Ceiling — GSJ. Self-closing hinges on doors at MC. Replaced warped pressed wood louver doors by kitchen with new wood doors and reinstalled hardware correctly. Reoriented Grotto roof. Electrical/Plumbing. New landscape lighting along MC pool. Repaired landscape lighting everywhere including main feed where desal trench was dug. Water heater replaced — GSJ. Bulb replacements. Flushed water systems at master bath. Permanent lighting to all dock structures. Moved electrical, vanities, installed sink plumbing to ready cabanas - LSJ. Engineering. Pressure wash karts, rock crusher, car mixer. Cleaned back rooms of wreck shop. Changed attachment, flat tires, other maintenance on lull JLG. Continued work on ambulance. Parts order w/Daphne. Repaired water tank. Assisted w/barge runs, haul away old mule, batteries, locate tech-ambulance. Assist w/removal and replacement — light generators from beach. Heavy Equipment. Closed existing pit. Grated roads - both islands. Beach Cleanup — both islands. Jackhammered stone, outcropping to smooth beach — GSJ, cleaned rocks off beach. Assist with moving shipments on barge. Fuel truck for diesel filled and to GSJ. Housekeeping. In addition to usual rounds - GSJ and LSJ, Cleaned out, moved Cabana items out of gym, ballet room — clean and up. Cleaned out, moved furniture, set up Cabanas. Landscaping. Worked with Boschulte overall landscaping, improvements. Layout for new flower bed at MC Pool. Moved rest of turpentines. Moved some palms from