From: Richard Kahn To: Jeffrey Epstein <[email protected]> Subject: GSJ Generator Date: Thu, 08 Nov 2018 20:52:25 +0000 update from Mike Richard Kahn Begin forwarded message: From: michael glidden Subject: Re: LSJ fuel readings Date: November 8, 2018 at 3:48:11 PM EST To: Richard Kahn < Cc: >, LSJ GSJ Both gensets are sitting next to the Q hut awaiting a crane to set them in their permanent location. The crane was cancelled due to the barge being out of service last week. The crane operator is off island until 11-14. I will call him then to get on his schedule asap. After getting them set they should be on-line within a week. Once the Q hut is extended around and over them some exhaust work will need to be done and should be completed in 3- 4 days. On Mr Epstein's last visit we were told that the Q Hut and generator were too close to the pool area and they both should be moved further away. That is currently being layed out as to location and cost. On Nov 8, 2018, at 12:51 PM, Richard Kahn < wrote: please respond to emails the same day you receive as mr epstein has discussed with you many times.. what is the status of GSJ generators?? Richard Kahn EFTA01017260