From: Richard Kahn To: Jeffrey Epstein <ieevacation(u:gmail.com> Subject: 9 east status report from Mark and Rich B Date: Thu, 26 Sep 2013 15:59:12 +0000 fyi Richard Kahn HBRK Associates Inc. 575 Lexington Avenue, 4th Floor, New York, New York 10022 tel fax cell Begin forwarded message: From: Richard Barnett < Date: September 26, 2013 11:32:33 AM EDT To: Mark Tollison < >, Subject: RE: Status Mark here is the up date of pending work. 1) Fire alarm control installation to start 8:00am with Stanley Security , 2) Motors for cooling tower shipped out to Landover cooling tower on 9/21 if Landover receives motors by 9/27 Installation will start week of 10/1 , 3) Heat exchangers priced control valves with Siemens looking into more cost effective solution. Control company scheduled to look at system on 10/4. to price valves. 4) Marantz receiver is covered under Warranty Technetron waiting on parts unit should be repaired by end of next week 10/4. 5) Front door contacted both contractors Simply Elegant. can do work for the same price from the proposal dated 4/11/12 cost $7800.00 Elite Renovation option 1) $ 10.800.00, Option #2 $ 15.800.00 Elite does not know if they can do the work they have a very busy work load until the end of the year and also price would be higher due to the front door is in worse condition. Project needs approval to proceed. From: To: Subject: Status Date: Wed, 25 Sep 2013 17:14:02 -0600 Rich, Please provide status on quotes/progress: 1. Fire alarm system control panel 2. Motors for cooling tower 3. Heat exchanges EFTA00971615