From: ' ' < To: Jeffrey Epstein <[email protected]> Subject: Re: VI Gunite Date: Tue, 10 Jan 2012 20:21:47 +0000 Ok Sent from my iPhone On Jan 10, 2012, at 4:11 PM, Jeffrey Epstein <jeevacation®gmail.com> wrote: begin work 15th feb On Tue, Jan 10, 2012 at 5:02 PM, brice gordon I FYI Tom, Darren and I spoke with Rex this morning > wrote: Continent on blue plaster availability for flag pool, which will be confirmed 2 pm today AST recommend this basic schedule starting this week green light material order/empty pool- 3 wks for tile main compound pool delivery, 2 weeks blue plaster flag pool heater relocation and start flag pool refurbishment replaster flag pool/ fill main compound material arrives/empty main compound pool tile main compound pool/ fill 7 - 8 week duration total for both pools work schedule, if required 7 days a week with option to start early and finish later than 4pm payment schedule will be confirmed once availability of plaster is confirmed today are you ok with this please advise Little Saint James USVI Phone: EFTA00674523