From: Leighton Allenby To: Jeffrey Epstein Cc: Anna Rodriquez , NYC - Richard Kahn LSJ - Danny Vicars Leighton Allenby Subject: Updated timeline for LSJ - August 11, 2015 Date: Wed, 12 Aug 2015 01:54:37 +0000 Hello Mr. Epstein, Please review updated timeline below. Cabana 1 & 2 1. Stone work and grout/mud completed today by Omar 2. Install shower heads and valves on Wednesday/Danny V & Danny E 3. AC replaced Wednesday by ReefCo - cabana 1 4. Soap holders not rusted - need cleaning/polishing/house cleaners 5. Remove bed to steam clean and remove pads on Thursday AM 6. Mold remediation on Thursday by ReefCo 7. Number One Steam - clean carpets on Thursday 8. Install new pads for rugs, install rug and bed - Friday AM 9. Clean entire cabana 1 & 2 on Friday AM to afternoon Cabana 2 & 3 1. Remove bed to steam clean and remove pads on Thursday AM 2. Mold remediation on Thursday by ReefCo 3. Number One Steam - clean carpets on Thursday 4. Install new pads for rug, install rug and bed - Friday AM 5. Clean entire cabana 1 & 2 on Friday AM to afternoon Mr. Epstein Bedroom floor 1. Pokey is laying floor, then sanding and finishing 2. Last coat of finish by 26th 3. Put room back together 28th and clean entire building Waterfall Project I. A realistic completion date is September I 8th/Chris and Peter will try° complete sooner 2. Track hoe leave tomorrow 3. Need to create (3) more falls - one day for each/Peter 4. Dig out retention pond and remove filUPeter 5. Install liner and rocks 6. Install electric, piping and pumps 7. Landscaping -TBD - not included in timeline 8. Lighting - TBD - not included in timeline Dock Fenders 1. 21st of August (Friday) for fenders, calking and touchup paint EFTA00650135