Outside Labor Budget # days Cost Per Day 5 Workers/Day Site Prep 3 $3,000.00 Surveying/Layout/Raise Well Cement Wall Elec Vault/Raise Well Form Layout/Construction 3 $3,000.00 Rebar/Wire Mesh Installation 3 $3,000.00 Concrete Pour/Finish Work 4 $4,000.00 Concrete Protection/Pour/Remove 2 $2,000.00 Forms Total Working Days is $15,000.00 Estimated Labor Budget: Total of 5 extra men neeeded: this is outside labor/rehire. Our crew will be working on g Repair of cement plan; excavation of soil needed to raise pad 4";etc On pour days we will need a total of 10 pp; 5 will come from permanent staff 15 working days per outside worker X $200 per day per worker X 5 workers = Note; We will know exact hires this week and determine their rate of pay based on who' Have got paid in the past. We can determine a more exact work schedule after we know workers speciality/talent. EFTA00594701