Globaltech Memorandum To: Emad Hanna/NYSG Subject: LSJ Pathway Lighting and Utility Trench Date: July 15, 2005 Prepared By: Paul Gandy/Globaltech Introduction We have prepared a preliminary selection and budgetary estimate for installing pathway lighting for all outdoor pathways at LSJ. The intent of the lighting project is to provide illumination of the immediate pathway area to allow visibility of all pathway segments at night. The original scope of the preliminary estimate was to provide information for the pathway lighting project only. However, it was brought to our attention that future utilities would be extended along the paths for irrigation water, potable water, power, communication and control, etc. For this reason it might be prudent to consider constructing the utility duct bank (all utilities in a common trench) at the same time as the lighting since similar construction equipment (trencher) would be needed for both projects. A summary of the two approaches follows: Description Construction Time Budget Estimate Lighting Only 4 months $ 430,000 Lightina and Ductbank 9 months $1,000,000 Each of the above amounts includes 10-20% for engineering, legal, and permitting fees. A detailed estimate of the above options is included in the attached spreadsheet. It should be noted that several preliminary assumptions were made in arriving at the scope of the project. Costs and scope could vary based on final design and project specifics. 4722 NW Boca Raton Blvd, Suite C103, Boca Raton, FL 33431 Telephone: 561-997-6433 Fax: 561-997-5811 EFTA00586314