Punch List — per JE directives as of January 6, 2012 1. Flagpole pool - Take the pool cleaners out done/delete - Scuppers are either rusted or broken — acknowledged by rex - Rug — date? - Outdoor lights 2. Banquette — two tree lights near banquette done 3. Gym - gutter is leaking in the front corner done 4. Flagpole bath and cabana — refrigerator 24" wide, 23" deep, stainless steel, and door swing on right — Brice ordered — robe hook outside shower —pool pump insulation for domestic fresh water distribution pump on order — walkway gates schedule — fridge due early next week, pump done, gates next week 5. Electrify Info center end of week for power and fans, data and phone 3 weeks out 6. Five Palms — stucco, window, hardscape, electrical 7. Grotto — lookout built with metal roof, landings - Greenhart wood — steps to Grotto 8. Heli wall 9. Heli garage 10. Big wind doors lighting - 2 recessed ceiling lights centered on each side of the doors — set on sconce timer 11. St. John terrace lights — change lights, 4 weeks 12. Hangar —floor sanding in progress — 40'X50' area for slab, 3 foot wall around it — containment for ISO fuel tank — bathroom and room divider — subcontractor? 13. Plants bought from Italian woman done 14. Steel shed for the new workshop area tom 15. Triangle 16. Entry tree lights, will have demo setup for next visit 17. Pebble beach - Solar fridge, light, fan for pebble beach 4 weeks out 18. Humidifiers — Atlanta Refrigeration speaking to Trane — this week 19. Yellow flowering Alamandra up Old Mill wall and Flagpole hill done 20. Beach 3 — containers into back of hill — Peter to grade out 21. Solutions for generators — no provisions for sound dampening — design fault — Maguire contract will be emailed to Gary, Tom, Darren, Brice for research into the matter — Brice adjusted shutter hurrican shutters closed 22. Fire system — not working, Brice creating fire charts for the island, minor adjustments, need review of operation