Punch List — per JE directives as of March 9, 2012 1. Rug — due to ship from manufacturer 3/7 2. Flagpole bath and cabana — slipcovers for sofa and cushion week of the 27th - photos for Flagpole bath and kitchen - white chairs in Flagpole should get orange piping - Sarah - get desk set - Brice - neither Ipad, no charge and no internet in Flagpole 3. Five Palms — stucco, window, hardscape, electrical - solar estimate Mar 9th - Floor - Doors location and fabrication -Lighting schedule - Electricity to run to Five Palms — Brice - what are our options? 4. Grotto - JE to redo layout of steps, determine shelter height — roof for Grotto shed 5. Heli garage — final punch out (painting) 6. Heli road - extend 7. Hangar —floor sanding in progress — 40'X50' area for slab, 3 foot wall around it — containment for ISO fuel tank — bathroom and room divider — subcontractor 8. Steel shed - have estimate for building, budget to be forwarded 31 Jan 9. Triangle, commenced work 10. Entry tree lights, confirmed ground lighting 11. Library Dehumidification — commences week of March 12 12. Solutions for generators —drawings complete for bid package 13. Top of hill — CLEAN UP — remove rocks and hydroseed 14. Tree order — develop list 15. Tiki - Shields — check with Sarah for date - Dock box pending available time 16. Sunken garden berm - continues 17. Concrete roads at flagpole - continues 18. Concrete triangle, 19. Bench placements — bench on peninsula point 20. Engineering clean up - continues 21. New vehicles — two more Polaris bikes (800's) — Larry/Brice 22. Dock decking — discuss pressure treated timber and carpeting 23. Aquarium photo — ordered for small shutters — check with Sarah for date 24. Mgrs Cottage Roof work remains — completion 2 weeks 25. Mooring Permit — proceeding with bids to place anchors 26. Electrical quotes - forward to JE 27. Rationalize Telephone system — Karen to make up extension list for each phone 28. Gates to hide eng