CONSTRUCTION CHANGE ORDER MAIN HOUSE 2-24-2011 The following is the additional scope of work at the main compound,we will have budgets asap Sand and seal main house deck Living room Coral work to bury elect.,phone,data and theater wiring New Elect fixtures and wiring Refinish floors Little office Demo bath and wood floor Redo elect,data,tele Install new liting Plaster repairs for redone elect and demo Paint celing white Install new coral stone floor,sand and seal Replace shutters in doors with glass Install inside shutters New 13x19 bath building attached to little office New pool at compound Demo old pool Construct new pool and deck EFTA00583546