Three week look ahead to OCT.7 MASTER 1. Walls and ceiling painted. 2. Floor leveler applied. 3. Floor underlayment down prepared for wood flooring. 4. Thassos going on walls 5. Coral laid up to shower, patched around columns COTTAGES 1. Roofs painted 2. Cabinets set tops on 3. Ion painting walls 4. Doors and shutters complete on tt2 in progress on 1&2 5. Baths complete 6. Ac operational KITCHEN 1. Walls standing 2. Roof framing starting LAUNDRY 1. Forms stripped 2. Stairs formed and poured. 3. Stone veneer 50% done 4. New road at grade for approval 5. Jeffrey drive walls mocked up for approval. 6. Interior walls being plastered. EFTA00583514