Little Saint James Island Greater Saint James Island Project No: LSJ-717 - Site Visit July 12-16, 2017 Observations and Recommendations Introduction I would like to thank the Owner and Management staff for the opportunity to consult on your project. There are many facets to this operation that have been observed, and many yet to be reviewed. The commentary offered in this report will be twofold. First, an overview of the operation, facilities, and staffing. Second, review of specific areas in current phase of development with observations and recommendations for your consideration. The opening remarks will be general in scope to provide a basis for the ensuing observations, critiques, and recommendations. Observations Operations LSJ has been in development for some time now and most of the existing sites appear to be very near completion stage. An extensive punch list remains and many ongoing improvements as well as future plans were observed and discussed. The success of the operation is dependent on adequate facilities and resources to support the owner's vision. Due to the remote nature of this site there are unique challenges to assemble the necessary components which have been adequately addressed and assurance that resources are not an issue to meet future needs. Facilities Proper facilities are necessary to ensure the success of any project. The physical plant, maintenance and construction facilities and available resources are impressive and well planned. A tour of all the maintenance and support sites was accomplished and comments and examples will be provided further on in this report. Staffing This is what drives the engine. A professional and motivated staff will utilize the previous two elements and make or break your project. I have known and worked with Mike and Kim Ross for many years and know them to be a hard working, dedicated team. Two days is obviously not long enough for an honest evaluation of any other staff but la