3nd Sept. 2005 Motor vessel PLAN B Weekly Report Monday 29th * A-Frame: design & concept drawings • Clear bridge equip. for refinishers. • Order 18' carbon passarelle from GMT composites, Rhode Island. • Timeline meeting with Chuck ADD • Atlas power equipment laoded aboard. Tues 30th * Remove anchor plates & prepare surface for new S/S plates • Cutting drain plumbing in new crew mess. • Bow rails removed for new installation of 2" extrusion. • Remove hydraulic power block assembly from steering flat. • Stb. side of owners stateroom staining complete. • Pump room pipework complete. • Replacing greatroom floor sections after removal for hotwork. Wed 10th • Drawings & layout of laundry/ crew cabin arrangement toward keeping Stb. Side room as a dry store. Discussed with Murrays. • Drawings in from Murrays for hot tub construction. • Anchor chain marks painted. • Rudders bearings replaced & rudders ready to reinstall. • Main engine heat exchangers return to yard & loaded aboard. • Bridge woodwork taped up & being prepared for refinishing. • Preparing forward hatch on lower deck level for cutting of coaming & plating up. • In consultation with Murrays & Lloyds about Lloyds requirements for cofferdams around stabilizer fin actuator components. Thurs 11th • Meeting with Allan Barr at yard re: timeline,contractors. Allan has indicated that he may want the color changed in the owners stateroom from the originally accepted sample to a darker tone?? This would be at extra cost! I have the original email sent to the vendor stating which color is to be used. • Lay out underwater lights & cameras. • Demonstration of the thermal cameras. • Sourcing vendors for the aft main deck canvas canopy. • Order gym equipment. Frichn 12th • Manouvre steel deck plate into position on main Deck where the swimming pool was removed. • Helideck extension nearly finished in fab shop. Due for priming early next week & into position by