MAHO BAY USVI, LLC: Construction Schedule ST JOHN, USVI ID Task Name Duration Start Finish Complete 1 Pool Shade Structure & Engineering Doors 45 days Mon 6/10/19 Fri 8/9/19 0% 2 Engneering doors removal and installation 5 days Mon 6/10/19 Fri 6/14/19 0% 7 Long Lead Procurement 14 days Wed 5/29/19 Mon 6/17/19 0% 8 6" Square or 4"x6" structural steel tube 2 wks Wed 5/29/19 Tue 6/11/19 0% 9 Mobilize on Site 2 days Mon 6/10/19 Tue 6/11/19 0% 10 Delivery of Trash Bin or bins to LSJ 1 day Thu 6/6/19 Thu 6/6/19 0% 11 Delivery of doors to site location and installation 2 days Mon 6/10/19 Tue 6/11/19 0% 12 Demolition of existing Pool Shade structure 2 days Mon 6/17/19 Tue 6/18/19 0% 13 Demolition of existing conc. Slab for new footing 2 days Wed 6/19/19 Thu 6/20/19 0% 14 8 -New Column Footing 7 days Fri 6/21/19 Mon 7/1/19 0% 15 Steel Reinforcement and poured conc. Footing 3 days Fri 6/21/19 Tue 6/25/19 0% 16 Form work for( 8) 16" square concrete columns 2 days Fri 6/21/19 Mon 6/24/19 0% Task Finish-only Split External Tasks Milestone External Milestone • Summary Deadline Project Summary Critical Inactive Task Critical Split Inactive Milestone Late Page 1 of 6 Inactive Summary Baseline Manual Task Baseline Milestone O Duration-only Baseline Summary Summary Rollup Progress Manual Manual Progress Manual Summary Start-only Slack EFTA00305825